Bill Per Visit on a Monthly Invoice

Price a plan per stop and send one invoice a month that lists the visits actually completed — per site, for a property manager with several homes.

Updated November 11, 2026

A property manager who pays $34 a stop for each of six homes does not want six invoices a week, and does not want a flat monthly price that ignores a five-visit month. With the service row's How it bills set to A rate and Price is to Per visit (billed monthly), the plan carries the per-visit rate, one invoice goes out a month, and it lists each home with the number of visits completed and the rate — Routine service — 1021 Three Forks Ct — 4 visits (November 2026), 4 × $34.00.

Pool companies see the plan as a Maintenance Plan; aquatic companies as a Pond Contract. The setting works the same everywhere.

Before you start

  • The contract's When to create invoices must be Monthly on a fixed day. Per visit (billed monthly) is only offered there; After each visit is the schedule that makes one invoice per visit.
  • The plan needs a visit schedule OpsVara can count — a visit interval, set weekdays, or a number of visits per period. Without one the row cannot be saved as per visit. On a new contract, Visit Schedule starts at the work type's own schedule (every 7 days for pool Routine Service) or the contract template's. Check it matches what the customer bought: the visit count, and so the forecast, comes from it.
  • Set Company time zone under SettingsCompany. A visit counts in the month it was checked out in that time zone. Left blank, OpsVara uses UTC, and a stop finished on the evening of the last day of the month moves to the next invoice.
  • The invoice always covers The month just finished. A per-visit month can only be counted once it has ended, so a plan with a per-visit row bills in arrears — see Bill the Month Just Finished.
  1. Set the rate per visit

    On New Contract, or under Service Scope on the contract, add or edit the service row. Set How it bills to A rate, then Price is to Per visit (billed monthly), and enter the per-visit amount. Price is shows only while the row is A rate. The preview reads the forecast for the term: $34.00 / visit × ~52 visits = $1,768.00 for the term (forecast — each month bills the visits completed).

  2. Price each site when they differ

    For a manager whose homes are priced differently, click Advanced Billing on the row, set Price applies to to A different price per site, and fill the Price at Each Site grid that opens with the price, above Advanced Billing. Price applies to shows once the contract has two or more sites. Each site then gets its own line on the invoice at its own rate. A site left blank on the grid is covered at no charge and gets no line.

  3. Choose the month the invoice covers

    Under Invoice Options, Bill For is locked to The month just finished (arrears) with the note Per-visit prices bill the month just finished. The invoice on the 1st bills the visits completed the month before. OpsVara sets this when you save, even if the company default bills the month the invoice goes out in. Set First Billing Month when the customer moved over mid-term and already paid the earlier months elsewhere.

  4. Save and read the plan

    Each monthly slot shows its forecast: the rate times the visits the schedule expects that month, one line per site. The Contract total shows the forecast with the note (forecast — per-visit months bill what was completed).

What happens on the billing day

On the billing day OpsVara drafts the month's invoice from the visits actually completed, not from the forecast. Under The month just finished the draft is made on the billing day, once the month has ended in your time zone (early morning in US time zones), so the last evening's stops are on it:

  • Every completed visit of the plan's work type in the month covered is counted, per site, by the day it was checked out in your company's time zone — or, for a visit completed without a check-out, the day it was scheduled. Only the visits that get a line are attached to the invoice. A linked job of another type, such as a repair, is not a visit and stays unbilled on its job, so invoice it from the job; the draft's internal note names each one. A One-Off Job set to No charge is never counted and never billed; one set to Per visit is billed from its job page; one set to Count against contract is a visit like any other.
  • Each month bills at most the visits the agreement's schedule can place that month, per site: the exact run days for set weekdays, the count × weeks for a weekly frequency, or one visit per interval for an every-N-days schedule. Extra completed visits stay on the plan but are not billed, and the draft's internal note says so — for example October 2026: 6 visits were completed at Main St and 5 are billed; the agreement places at most 5 that month. The 1 extra visit is not billed. A stop pinned to more route days than agreed is served too often: check its saved routes under Dispatch → Saved Routes → Health.
  • The cap does not apply to lake contracts or to schedules with seasons. On a plan that invoices After each visit instead, extra visits still draft an invoice, but that draft is held — see Automatically Send Draft Invoices.
  • A visit at a site the row gives no price, or a site outside the row's scope, gets no line and stays unbilled on its job. The draft's internal note lists each one by job number, site and day. If you later add a per-visit price for that site, the next draft bills those earlier visits too, each month as its own line.
  • On a plan that also has a flat row that bills at every site — A rate at Per month with Applies to Every site, or Part of the plan price (stored as Billed as Included under Advanced Billing) — a visit the per-visit row does not price, at a site the flat row prices, is already paid for by the flat line. It is attached to the monthly invoice with no line of its own, is not listed in the internal note, and its chemicals are billed on that invoice.
  • Each site becomes one line: the site, the visit count, and the month, at that site's rate.
  • The drafted slot is updated to the real amount, so the Contract total and the plan reflect what was billed; the months still to come stay forecasts.
  • A visit that reaches OpsVara after the invoice was drafted — a phone that synced late, or a visit marked complete afterwards — is billed on the next invoice rather than lost, as its own line named for the month it counts in: the month it was checked out (a stop checked out after midnight counts in the new month), or, for a job completed without a check-out, the month it was scheduled.
  • The agreement's last month has no next invoice. OpsVara tries it again every day from its billing day until it is drafted, for up to a month after the end date, so a visit that syncs a few days late is still on it. If you void the last month's invoice, OpsVara does not draft it again; create it from the contract if it still needs one. A visit that arrives after the last month was drafted stays unbilled on its job; OpsVara sends your office users one Visits completed after the last invoice notification per contract with the number of such visits, and you invoice them from the job.
  • A month with no completed visits is not drafted; its slot stays planned. A plan that also has a flat row — Per month, or a price for the whole term — still owes the flat amount for that month: once the month has finished, the billing day drafts the flat amount on its own, and + Create Invoice does too. A visit of that month that syncs after the draft goes on the next month's invoice, with its date. The plan's last month is the exception, because no invoice comes after it: its billing day waits for a visit and keeps trying, and + Create Invoice refuses it (No completed visits to bill for Monthly billing 2026-11 (billed 2026-12-01) yet.). Two forced paths draft the flat amount on its own: Create anyway on a month that has not finished yet (see below), and Bill It Now, Then Archive when you archive the contract. Otherwise the last month's flat amount has to go on an invoice you make by hand.
  • The last month of the term is billed on the billing day after the term ends, even though the contract reads Completed by then.

The draft lands under Sales and BillingInvoices for review like any other scheduled invoice.

Creating the invoice early

+ Create Invoice on the contract refuses a per-visit month that has not finished: This month is not finished yet — the invoice for Monthly billing 2026-11 (billed 2026-12-01) is available on 2026-12-01. Click Create anyway to bill the visits completed so far on an early invoice of its own. The month's own invoice still drafts on its billing day for the rest of that month's visits, less what the early invoice billed, so the contract total doesn't change. Chemicals stay on the month's invoice. Voiding the early invoice puts its amount back on the month's invoice.

Archiving a plan mid-month

Once a plan is archived, cancelled or paused, its billing day no longer drafts anything, so the visits already completed in a month that has started would never be billed. When you Archive a plan that has completed visits not yet on an invoice, OpsVara asks first and lists each month with a checkbox, its visit count and an estimated amount. A month with completed visits starts ticked, also when it is still in progress. Untick a month you do not want billed. Bill It Now, Then Archive creates a draft for each ticked month from the visits completed so far (as Create anyway does), then archives. The visits of a month you left unticked stay off those drafts, the customer's activity gets a note saying the month was left unbilled, and the visits stay billable from their jobs. Archive Without Billing archives and leaves that note for every month listed. With no month ticked the button reads Archive Without Billing, because nothing would be billed. If a month already has an invoice and more of its visits were completed late, they can only go on a later month's invoice. When that later month is on the list it says "its invoice also bills the late visits from" the earlier month "when that month is ticked"; if you untick it and keep the earlier month ticked, OpsVara tells you which month to tick. A later month that has ended, or that has completed visits of its own, starts ticked. A later month that is still in progress with only its flat monthly fee always starts unticked and reads "in progress — ticking bills the full month"; the earlier month then starts unticked too and reads "already invoiced — its late visits go on the invoice for" that month, "tick both to bill them". Leave both unticked and the late visits stay billable from their jobs. When the later month is not on the list (nothing of its own to bill), its invoice is used for the late visits without asking. If one month's draft cannot be made, the months already drafted stay drafted and your ticks for the rest stay as you left them. A plan with a flat monthly fee beside the per-visit price is asked about the month too, even before its first visit: Bill It Now then drafts the fee for that month. Create anyway on a month still in progress with no completed visits does the same. With no fee and no visits there is nothing to bill, and OpsVara archives without asking.

Chemicals and combined invoices

A rate quoted "with chemicals" already includes them. Leave SettingsChemical Billing off for these customers, or the monthly invoice adds chemical lines on top of the per-visit rate. Auto-combine under SettingsAutomations folds a customer's other open drafts into a new one, so keep it off for a work type billed this way unless you want that.

Verify it worked

  • Open the contract. Each planned monthly slot lists one line per site with a visit count and the rate, and the total carries the forecast note.
  • Complete a few visits, then on the billing day open the draft under Sales and BillingInvoices: the line items show the real visit counts, and the contract's slot for that month now holds the same amount.
  • Re-running the billing day does nothing: a slot that already holds an invoice is skipped.

Frequently asked questions

The contract total looks wrong. It changes when I change the visit days.

On a per-visit plan the total is a forecast — the rate times the visits the schedule expects over the term. It is there to size the agreement, not to bill from. Each monthly invoice bills the visits that were actually completed, and the drafted slot then holds the real amount.

I clicked Create Invoice on the 15th and OpsVara refused.

The month has not finished, so its visit count is not final. Wait for the billing day, or click Create anyway to bill the visits completed so far on an early invoice of its own. The month's own invoice still drafts on its billing day for the rest of that month's visits, less what the early invoice billed, so the contract total doesn't change. Chemicals stay on the month's invoice. Voiding the early invoice puts its amount back on the month's invoice.

A stop finished at 8 PM on the last day of the month showed up on the next month's invoice.

Check Company time zone under Settings → Company. OpsVara counts each visit in the month it was checked out in that time zone; with it left blank it uses UTC, where 8 PM Eastern is already the next day.

A repair job at one of the homes was linked to the plan. Was it billed as a visit?

No. Only jobs of the plan's own work type count as visits, and only visits that get a line are attached to the monthly invoice. A linked repair stays unbilled on its job, so invoice it from the job as usual; the draft's internal note names it by job number, work type and day. A job the plan scheduled itself, such as a Care Schedule task on its own work type, is the plan's own work — it is attached to the invoice with its ticked extras and chemicals, but is not counted as a visit.

A courtesy re-visit was entered as a One-Off Job set to No charge. Was it counted?

No. A One-Off Job set to No charge is free, chemicals and extras included — it is not counted as a visit and is on no invoice; if it had an extra ticked or chemicals logged, the draft's internal note says they were left off as marked. One set to Per visit is not counted either; invoice it from its job page, and the draft's internal note names it. One set to Count against contract is one of the plan's visits at the per-visit rate.

Why can't I change Bill For on a per-visit plan?

A per-visit month can only be counted once it has ended, so a plan with a Per visit (billed monthly) row always bills the month just finished. Bill For is locked while the row is there and unlocks if you remove the row, or change its Price is or How it bills. Creating the contract, saving its Invoice Options or Service Scope, renewing it, or importing it sets this for you. An older contract changes when you next save Invoice Options.

A visit at one of the homes wasn't on the monthly invoice.

A visit at a site the row gives no price, or a site outside the row's scope, gets no line. It is left unbilled on its job, and the draft's internal note lists it so you can invoice it from the job or add a price for that site. If the plan also has a flat Per month or term row that prices that site, the visit is covered by the flat line instead — it is attached to the invoice with no line of its own and is not listed.

Can a quote offer Per visit (billed monthly)?

Yes, on a quote that bills monthly. The customer's quote shows the rate times the visits the schedule expects, marked as an estimate, and approval creates the per-visit plan. A quote that adds to or replaces a monthly contract can use it too — adding a home to a property manager's plan, say. Its estimate counts that contract's visits from today to the end of its term, and the new home gets its own price on the contract. A dollar discount on a quote that adds to the contract comes off the estimate the customer saw, spread across those visits ($50 off a $340 estimate prices each visit at $29). Send stops a quote that replaces the contract with a dollar discount (use a percent discount, or price the line Per month or for the term), and a quote that adds a per-visit price for a service the contract already bills at one Per month price (change that price on the contract itself, or send a quote that replaces the contract). The contract must bill the month just finished; if it bills the month the invoice goes out in, Price is on that quote's lines does not offer Per visit (billed monthly), and a line that already has it says why and will not send — change Bill For in the contract's Invoice Options first, or price the line Per month. A quote sent before October 2, 2026 keeps its per-visit line as a fixed amount for the term.

Why did my invoice bill fewer visits than were completed?

Each month bills at most the visits the agreement's schedule can place that month, per site — the exact run days for set weekdays, the count times weeks for a weekly frequency, or one visit per interval for an every-N-days schedule. Extra completed visits stay on the plan but are not billed, and the draft's internal note says so (for example October 2026: 6 visits were completed at Main St and 5 are billed; the agreement places at most 5 that month. The 1 extra visit is not billed). A stop pinned to more route days than agreed is served too often — check its saved routes under Dispatch → Saved Routes → Health. Lake contracts and schedules with seasons are not capped. On a plan that invoices after each visit instead, extra visits still draft an invoice that is held — see Automatically Send Draft Invoices.